FAQ: LT Connection

Q.What is the tariff for LT category VIII (Temporary Supply)...

Q.What is the tariff for LT category VIII (Temporary Supply)?

LT Category VIII –Temporary Supply:

       Fixed charges 21/kW, energy charges 10.00 per unit.(TS)

       Fixed charges 21/kW, energy charges 9.90 per unit.(AP)

Q.What is the tariff for LT category VII (General)?

Q.What is the tariff for LT category VII (General)?

    LT Category VII – General:

  1. LT VII (A) - General Purpose;

           Fixed charges 21/kW, energy charges 6.90 per unit.(TS)

           Fixed charges 21/kW, energy charges 6.86 per unit.(AP)

     b.  LT VII (B) – Religious Places;

          Fixed charges 21/kW, energy charges 5.00 per unit.(TS)

          Fixed charges 20/kW, energy charges 4.70 per unit.(AP)

Q.What is the tariff for LT category VI (Street Lighting & P...

Q.What is the tariff for LT category VI (Street Lighting & PWS)?

LT Category VI – Street Lighting & PWS:

            LT VI (A)-Street Lighting;

  1. Panchayats.

           Fixed charges 32/kW, energy charges 5.70 per unit.(TS)

           Fixed charges 32/kW, energy charges 5.64 per unit.(AP)

     b. Municipalities.

           Fixed charges 32/kW, energy charges 6.20 per unit.(TS)

           Fixed charges 32/kW, energy charges 6.16 per unit.(AP)

     c. Municipal Corporations.

           Fixed charges 32/kW, energy charges 6.70 per unit.(TS)

           Fixed charges 32/kW, energy charges 6.69 per unit.(AP)

            LT VI (B) - PWS Schemes:

   a)   Panchayats.

          Fixed charges 32/kW (subject to a minimum of Rs 50/month), energy charges 4.60 per unit.(TS)

           Fixed charges 32/kW, energy charges 4.59 per unit.(AP)

  b)   Municipalities.

           Fixed charges 32/kW (subject to a minimum of Rs 100/month), energy charges 5.70 per unit.(TS)

           Fixed charges 32/kW, energy charges 5.64 per unit.(AP)

  c)  Municipal Corporations.

           Fixed charges 32/kW (subject to a minimum of Rs 100/month), energy charges 6.20 per unit.(TS)

           Fixed charges 32/kW, energy charges 6.16 per unit.(AP)

Q.What is the tariff for LT category V (Agriculture)?

Q.What is the tariff for LT category V (Agriculture)?

    LT Category V – Agriculture:

          LT - V (A) – Agriculture with DSM Measures

  1. Corporate Farmers & IT Assesses: charges collected are at 2.50 /unit.(TS & AP)
  2. Wet Land Farmers (Holdings more than 2.5 acre)

             Fixed charges 525/HP/Year, energy charges 0.50per unit.(TS & AP)

     c.  Dry Land Farmers (Connections more than 3 nos.)

             Fixed charges 525/HP/Year, energy charges 0.50per unit.(TS & AP)

     d.  Wet Land Farmers (Holdings less than 2.5 acre) , Dry Land Farmers (Connections lessthan 3 nos)-No charges are collected.(TS & AP)

         LT - V (B) – Agriculture without DSM Measures:

      a) Corporate Farmers & IT Assesses: charges collected are at 3.50 /unit.(TS & AP)

      b) Wet Land Farmers (Holdings >2.5 acre)

             Fixed charges 1050/HP/Year, energy charges 1.00per unit.(TS & AP)

     c) Dry Land Farmers (Connections > 3 nos.)

             Fixed charges 1050/HP/Year, energy charges 1.00per unit.(TS & AP)

     d) Wet Land Farmers (Holdings <= 2.5 acre), Dry Land Farmers (Connections <= 3 nos);

             Fixed charges 525/HP/Year, energy charges 0.50 per unit.(TS & AP)

         LT V(C) – Others:

  1. Salt farming units with CL up to 15HP;

             Fixed charges 20/HP, energy charges 3.70 per unit.(TS & AP)

      b.  Rural Horticulture Nurseries upto 15HP;

             Fixed charges 20/HP, energy charges 3.70 per unit.(TS & AP)

Q.What is the tariff for LT category IV (Cottage Industries)...

Q.What is the tariff for LT category IV (Cottage Industries)?

     LT Category IV – Cottage Industries:

  1. Cottage Industries up to 10HP;

            Fixed charges 20/kW (subject to a minimum of Rs 30/month), energy charges 3.75 per unit.(TS)

            Fixed charges 20/kW, energy charges 3.75 per unit.(AP)

     b.  Agrobased activity up to 10HP;

            Fixed charges 20/kW (subject to a minimum of Rs 30/month), energy charges 3.75 per unit.(TS)

            Fixed charges 20/kW, energy charges 3.75 per unit.(AP)

Q.What is the tariff for LT category III (industry)?

Q.What is the tariff for LT category III (industry)?

         LT Category III – Industry:

  1. Industries:

            Fixed charges 53/kW, energy charges 6.40 per unit.(TS)

            Fixed charges 53/kW, energy charges 6.38 per unit.(AP)

      b. Seasonal Industries (Off Season):

            Fixed charges 53/kW, energy charges 7.10 per unit.(TS)

            Fixed charges 53/kW, energy charges 7.09 per unit.(AP)

      c. Pisciculture/Prawn culture:

            Fixed charges 21/kW, energy charges 4.90 per unit.(TS)

            Fixed charges 21/kW, energy charges 4.63 per unit.(AP)

      d. Sugarcane crushing:

            Fixed charges 21/kW, energy charges 4.90 per unit.(TS)

            Fixed charges 21/kW, energy charges 4.63 per unit.(AP)

      e. Poultry farms:

            Fixed charges 50/kW, energy charges 3.60 per unit.(TS)

            Fixed charges 53/kW, energy charges 5.63 per unit.(AP)

      f. Mushroom & Rabbit Farms:

            Fixed charges 53/kW, energy charges 6.00 per unit.(TS)

            Fixed charges 53/kW, energy charges 5.63 per unit.(AP)

      g. Floriculture in Green House:

            Fixed charges 53/kW, energy charges 6.00 per unit.(TS)

            Fixed charges 53/kW, energy charges 5.63 per unit.(AP)

            

Q.What are the other categories in LT connection?

Q.What are the other categories in LT connection?

       The other categories in LT are:

            LT Category III----Industry.

            LT Category IV----Cottage Industries.

            LT Category V ----Agriculture.

            LT Category VI----Street Lighting & PWS.

            LT Category VII---General.

            LT Category VIII--Temporary Supply.

Q. How can I report frequent unscheduled load shedding?

Q. How can I report frequent unscheduled load shedding?

      If a very frequent load shedding is observed, it is to be reported to concern Divisional Engineer (operations).

Q. How can I report for interruptions or failure of power su...

Q. How can I report for interruptions or failure of power supply?

If any frequent interruption or failure of power supply is observed, complaints should be reported to fuse off call centers or customer relation management center or units (CRM).

Q. How can we rectify burnt/struck up or defective energy me...

Q. How can we rectify burnt/struck up or defective energy meters?

      If any problem like meter creeping / burnt / struck up / suspected defective is been sensed from the energy meters for LT services,

  1. A request application is to be given in the section office.
  2. Meter testing charges are to be paid by the customer in advance.
  3. If the meter is found to be defective while testing, the amount paid towards testing will be credited back to the customer’s account.   

Q. How can we request for bill payment in installments?

Q. How can we request for bill payment in installments?

 For Bill payment against LT connections, a request application has to be given to AAO/ERO and an additional charge of 42% per annum on the installment amount (18% additional charges due to belated payment + interest of 24% per annum).

Q. What is the procedure for shifting/installation of poles ...

Q. What is the procedure for shifting/installation of poles & lines?

Step 1: A representation has to be given in the section office with a consent letter enclosed for advance payment of shifting charges.

Step 2: Ownership document at new location along with a NOC from panchayat or municipality are to be produced.

    Step 3: Arrears of electricity charges are to be cleared.

    Step 4:  There shall not be any pending appeals / disputes filed by the customer.

Step5: Shifting charges are to be paid which includes cost of actual estimates plus 25% towards supervision charges.

Q. Can I change my LT power connection of single phase to th...

Q. Can I change my LT power connection of single phase to three phase connection?

Yes, you can change the  LT power connection  from  single to 3-phase and vice versa.  A representation has to be given in the section office along with a revised agreement and revised test report has to be signed stating all the additional loads. All the arrears of current consumption charges are to be cleared.

Q. What is the procedure for Change of Category Power Supply...

Q. What is the procedure for Change of Category Power Supply Connection?

The procedure for Change of Category

Application in duplicate shall be registered in concerned CSC with following documents in duplicate. Application Form

  1. Latest electrical bill with payment receipt.
  2. LT application -3 copies.
  3. Registration fee, 25/- for domestic purpose and 50/- for commercial & general purpose.
  4. Revised agreement and test report are to be signed.
  5. Additional consumption deposit is to be paid if it attracts higher tariff.
  6. Additional development charges, if any to be paid as per rules.

Q. How can we increase the connected load?

Q. How can we increase the connected load?

An application has to be registered in the concerned section office by paying an application fee upon which the development and service line charges are to be paid separately as per rules. Development Charges:

  1. For domestic :- Rs. 1000/- per KW
  2. For non-domestic:- Rs. 2000/- per KW

Service Line Charges:

It depends upon the work involved i.e., cost will be comparable as per the extension of service lines.

Note: - The minimum load required to convert is 3 KW for domestic load and 5 KW for commercial load.

Enclosures:

1.Wiring certificate (commencement & completion).

2. Latest electricity bill with payment receipt.

Q. How can the contracted load / demand be reduced / enhance...

Q. How can the contracted load / demand be reduced / enhanced?

  1. New agreement and revised test reports are to be signed after receipt of sanction from competent authority.
  2. Additional consumption deposits, service line and development charges to be paid as per rules.
  3. The application is to be given in the section office.

 

Q. What are the supporting documents which are to be submitt...

Q. What are the supporting documents which are to be submitted along with the application for registering a new service connection?

  1. For Domestic Purpose:-
  1. Proof of ownership (sale deed, allotment/possession lease deed, municipal tax payment receipt) or Proof of occupancy (lease/rental deed with land lord, electoral identity card or passport or PAN card with proof of ownership of land lord).
  2. Indemnity bond (A Rs.100/- stamp paper with a letter of consent from landlord to tenant/ lessee/ occupier).
  3. Wiring completion report (from a licensed electrical contractor) along with his details (name, license number, full address) to be filled within the application form.
  4. Test report.
  5. Demand draft for new connection.
  6. Latest municipal tax payment receipt.
  7. Nearest pole no
  8. Passport size photos-2 copies
  9. Municipal/panchayat plan approval copy

 II. For Commercial Purpose:-

  1. Proof of ownership (sale deed, allotment/possession lease deed, municipal tax payment receipt) or Proof of occupancy (lease/rental deed with land lord, electoral identity card or passport or PAN card with proof of ownership of land lord).
  2. Indemnity bond (Rs.100/- stamp paper with a letter of consent from landlord to tenant/ lessee/ occupier).
  3. Wiring completion report (from a licensed electrical contractor) along with his details (name, license number, full address) to be filled within the application form.
  4. Test report.
  5. Demand draft for new connection.
  6. Valid municipal license for running commercial establishment.

Q. What is the procedure to transfer the title for my LT con...

Q. What is the procedure to transfer the title for my LT connection?

The transfer of title in LT connection can be done in following steps.

Step  1: You have to download the title transfer application form respective DISCOM website or here.

Step  2: Duly fill the application form.

Step  3: Pay the charges as applicable

Step  4: Attach the necessary documents.

Step 5: If there are there are no previous dues and application in required format, then the application will be accepted.

Step 6: The change of consumer’s name shall be effected within two billing cycles after     acceptance of application.

Q. What is the system of supply and contracted load for LT c...

Q. What is the system of supply and contracted load for LT connection?

The type of Supply for Low Tension is A.C. 50 Cycles, three phase supply at 415 Volts or single phase supply at 240 Volts.

These tariffs are applicable for supply of Electricity to L.T consumers with a contracted load of 56 kW/75 HP and below. 

Q. What are the charges collected by DISCOM for the power co...

Q. What are the charges collected by DISCOM for the power consumed in Non-domestic/Commercial category?

The charges collected for the power consumed is as follows

     Fixed Charges: For all Lt II categories are 50/KW

     For Lt - II (A) category

     (Upto 50 Units/Month kwh/kvah) the charges collected are at Rs.5.40/unit.

     For Lt - II (B) category (Above 50 Units/Month kwh/kvah)

              First 50 kwh/kvah the charges collected are at 6.63 per unit.

              

              51-100 kwh/kvah the charges collected are at 7.38 per unit.

              101-300 kwh/kvah the charges collected are at 8.13 per unit.

              301-500 kwh/kvah the charges collected are at 8.63per unit.

              Above 500 kwh/kvah the charges collected are at 9.13per unit.

     For Lt - II (C) category (Advertising Hoardings)

              The charges collected are at 11.43/unit.

Q . What are the charges collected by DISCOM for the power c...

Q . What are the charges collected by DISCOM for the power consumed in domestic category?

The charges collected for the power consumed is as follows:

For Lt - I (A) category (Upto 50 Units/Month kwh/kvah) the charges collected are at Rs.1.45/unit.

For Lt - I (B) category (Above 50 Units/Month kwh/kvah up to 100 Units/Month kwh/kvah)

              First 50 kwh/kvah the charges collected are at 1.45 per unit.

              51-100 kwh/kvah the charges collected are at 2.60 per unit.

For Lt - I (B) category (Above 100 Units/Month kwh/kvah up to 200 Units/Month kwh/kvah)

              First 50 kwh/kvah the charges collected are at 2.60 per unit.

              51-100 kwh/kvah the charges collected are at 2.60 per unit.

              101-150 kwh/kvah the charges collected are at 3.60 per unit.

              151-200 kwh/kvah the charges collected are at 3.60per unit.

For Lt - I (B) category (Above 200 Units/Month kwh/kvah)

              First 50 kwh/kvah the charges collected are at 2.60 per unit.

              51-100 kwh/kvah the charges collected are at 3.25 per unit.

              101-150 kwh/kvah the charges collected are at 4.88 per unit.

              151-200 kwh/kvah the charges collected are at 5.63per unit.

              201-250 kwh/kvah the charges collected are at 6.38per unit.

              251-300 kwh/kvah the charges collected are at 6.88per unit.

              301-400 kwh/kvah the charges collected are at 7.38per unit.

              401-500 kwh/kvah the charges collected are at 7.88per unit

              Above 500 kwh/kvah the charges collected are at 8.38 Rs per unit.

Q . What is the type of category applied for domestic purpos...

Q . What is the type of category applied for domestic purpose?

The consumer who is having the monthly consumption Upto 50 units has to apply for the LT I (A) category and consumer having monthly consumption of more than 50 units has to apply for LT I (B) category.

Q.I need a 3 Phase connection for my house? What is the proc...

Q.I need a 3 Phase connection for my house? What is the procedure for getting a new service connection?

Step 1: You have to download LT application from respective DISCOM website or here.

Step 2: You have to apply for LT I category and fill in the details correctly in the application form in customer service centre.

Step 3: You have to attach following documents:

  1. Application fees (Demand Draft of  50/- In favor of Assistant Accounts officer of the concerned Electrical Revenue Office) ERO
  2. Proof of ownership of premises of the rental or lease deed.
  3. Permission of local bodies
  4. Wiring certificates (if ready)
  5. Consent letter of owner along with the Indemnity Bond for a period of two years in case the applicant is tenant

Step 4: After the receipt of application the department conducts the feasibility study for supplying the requisite power. 

Step 5: After the inspection or feasibility study is done a report is submitted to the concerned DE by the inspection personal and recommend for release of power.

Step 6: Concerned DE will issue release order. Metering and protection department will come and release the supply.

If you have any queries please write to us info@epowerone.com or post here.